Projects | Roads and Infrastructure | Dubai Investment Park - Phases 1 to 5

Dubai Investment Park - Phases 1 to 5

Client: Dubai Investments Park Development Co.
We have completed five individual phases of work at Dubai Investment Park over a 13 year period. A split between each phase is detailed below.

Phase 1 - 3 Months (1998)
Our scope consisted of bulk earthworks and disposal to an area of 3.1 million Sq. M.

Phase 2 - 10 Months (2003)
Our scope consisted of bulk earthworks, shifting and infrastructure to an area of 1.95 million Sq. M. and included 11.5 Km of roads, sewerage, irrigation, telecommunication networks and road crossing ducts for electricity, water and lighting.

Phase 3 - 8 Months (2004)
Our scope comprised the complete infrastructure works to an area of 3.8 million Sq. M including 16 Km of roads, sewerage, irrigation, lift stations, telecommunication network and associated works for electricity, water and lighting.

Phase 4 - 9 Months (2005)
Our scope comprised of 27 Km of roads, sewerage, irrigation, telecommunication network and road crossings for electricity, water and lighting.

Phase 5 - 39 Months (2006)
Our scope comprised the complete infrastructure works to an area of 7.1 million Sq. M. including 31 Km of roads, sewerage, irrigation, telecommunication network and road crossings for electricity, water and lighting.